Projects
Project: |
Mindarie Mineral Sands |
Client: |
RJ Robbins: |
When: |
2007 |

| 40m diameter Thickener: | |
|---|---|
| Tonnage: | 65t |
Consortiums involvement |
|
| Bowhill Engineering: | Head Contractor, detailing, material supply |
| Jacksons Australia: | Fabrication & welding of wall bases and transport to Horwood Bagshaw |
| Horwood Bagshaw: | Fabrication & welding of complete wall segments, blasting/painting, delivery to site. |

| Mobile Skidded Crib rooms x 2 | |
|---|---|
Consortiums involvement |
|
| Bowhill Engineering: | Head Contractor |
| Horwood Bagshaw: | Material supply, fabrication & welding of complete units, blasting/painting, delivery to site. |

| C4 Skid and Structural for PCP | |
|---|---|
| Tonnage: | 35t |
Consortiums involvement |
|
| Bowhill Engineering: | Head Contractor, material supply, fabrication & welding of 20t skid base, assembly and welding of pre fabricated/welded subcomponents for the structural section of work blasting/painting delivery of site in large sections. |
| Jacksons Australia: | Fabrication & welding of structural components/subcomponents blasting/painting of completed components and transport to site, delivery of subcomponents to Bowhill Engineering |

| Pipe Gantry | |
|---|---|
| Tonnage: | 100t |
Consortiums involvement |
|
| Bowhill Engineering: | Head Contractor, supply of materials, some blasting/painting. |
| Horwood Bagshaw: | Fabrication & welding of complete units, blasting/painting, delivery to site. |

| Area 40 Tank supports, handrails and walkways | |
|---|---|
| Tonnage: | 65t |
Consortiums involvement |
|
| Bowhill Engineering: | Head contractor |
| Jacksons Australia: | Material supply, fabrication & welding of complete units, blasting/painting, delivery to site. |